UTHPC - UT HPC Cluster Rocket and Slurm upgrade – Maintenance details

UT HPC Cluster Rocket and Slurm upgrade

In progress
Scheduled for 21. July 2026 at 6:00:00 –  31. July 2026 at 14:00:00UTC

Affects

rocket.hpc.ut.ee

Under maintenance from 6:00 AM to 12:00 AM

Services

Under maintenance from 6:00 AM to 12:00 AM

Galaxy

Under maintenance from 6:00 AM to 12:00 AM

RStudio

Under maintenance from 6:00 AM to 12:00 AM

Open OnDemand

Under maintenance from 6:00 AM to 12:00 AM

  • Update
    22. July 2026 at 13:40:21UTC
    Update
    22. July 2026 at 13:40:21UTC

    Update: Both login node updates have been completed successfully ahead of schedule. Login1 and Login2 are now fully available, and all temporary SSH connection restrictions have been lifted.

    Next, the Slurm upgrade on the 28th of July will follow. Until then, no interruptions in Rocket cluster computing are expected.

  • In progress
    21. July 2026 at 6:00:01UTC
    In progress
    21. July 2026 at 6:00:01UTC
    Maintenance is now in progress
  • Planned
    17. July 2026 at 12:08:06UTC
    Planned
    17. July 2026 at 12:08:06UTC

    Here is the summer maintenance schedule for the HPC Rocket Cluster.

    HPC cluster Rocket updates are scheduled for July 2026 to improve the cluster's performance and capabilities.

    1. Login Node Updates

    We'll be performing system updates on both login nodes on the following dates:

    * Login1: July 21st

    * Login2: July 28th

    To minimize disruption, we'll close new SSH connections to the corresponding login node one week before each update, allowing existing connections to naturally expire. One of the login nodes will remain available at all times, so you won't experience any service downtime.

    2. Slurm Update

    On July 28th, starting at 15:00, we'll be upgrading the Slurm version. Your running jobs won't be affected. However, during the update, submitting new jobs, SLURM commands like sacct, sacctmgr, and related tools will be unavailable. The process should take about two hours, but may run longer.

    The compute nodes will also receive OS, BIOS, and firmware upgrades.

    After July 28th, the compute nodes will be updated in a rolling fashion. This means some nodes will be temporarily drained until all updates are complete, which may result in longer queue times depending on cluster usage.

    The Open OnDemand service, as the UTHPC cluster portal, is also affected.